A recent major extension to the house now requires a garden to suit: providing an area for entertainment and easy use and access for the children.

January 2022

Garden prior to work starting

Week 1

Site clearance and levelling. Installation of sleepers and hardcore.

Week 2/3

Set up and lay out. Slot drain and land drainage installed with correct "Fall" to patio established.

Week 5

Porcelain tiling nearing completion with grouting done. Build of new raised seating and circular firepit area progressing

Completion - February 22