Garden in Crymlyn Parc. The clients want to be able to use all of their garden for their family and for the children they foster, some of whom are disabled. This makes the need for safety and accessibility paramount and for the garden to be on all one level. Currently the garden is very unsafe (see photograph of framing under the raised deck) in many areas as it has deteriorated badly over the years.

Garden prior to work starting:

Phase 1

January 21; Initial clearance

Phase 2:

January / February2021: Construction of new retaining wall and steel and timber frame for new Artificial Lawn.

March 21 - We had to move off site due to Covid and a planning query. Resumed work in January 22

Completion March 22